Staff Augmentation
Duane Arnold Nuclear Energy Center 
  • DEMCO was contracted to provide skilled instrument and control technicians to test, calibrate, and replace components integral to the function of critical and sensitive systems throughout the complex.
  • This work was accomplished as part of an accelerated critical path outage
General Electric Labor Support 
  • The plant includes two, natural gas fueled, GE 7H combined-cycle power blocks for a total maximum net rated electrical output of 775 MW. This marks the first installed application of the H System gas turbine technology in a 60 Hz machine, as well as the first installation in the
Prairie Creek Power Station 
  • DEMCO assisted Alliant, Tellus, and WGI with the rebuild and recommissioning of the flood damaged Prairie Creek Power Station. Damaged in the June 2008 flooding of the Iowa River, the Prairie Creek Power Station provides industrial steam and almost 250 mega watts of electrical
Nine Mile Point Nuclear Station Unit 1 
DEMCO was awarded a contract to provide I&C and AOV Technician Support Services for Unit 1 N1R20 Outage. DEMCO was required to perform the following services:
  • Perform maintenance, repair, calibration, testing, inspection, troubleshooting & evaluation on plant equipment.
  • Repair I&C